BlueSide – Latest news about construction

September 23, 2025

We have dismantled the tower crane and are installing it (electrical and mechanical) on all levels, the cladding and painting of the facade has been completed.

We are carrying out tinsmithing work, and the aluminum pergolas will soon be installed on both the street and interior facades.

The garden is being built, parquet flooring is being laid, cold coverings have been laid in the apartments and in the communal areas, grouting and silicone are also progressing.

The construction of the synthetic resin covering in the garage areas will begin soon and the garage doors will be installed soon.