Construction is progressing according to schedule, with structural works currently underway. The foundation slab has been completed across the entire footprint of the building, and the installation of the permanent dewatering pipe network and wells has also been successfully completed.
The structural works on the individual buildings are at different stages of completion. In Building A, construction of the ground floor ceiling slab is in progress. In Building B, work has already advanced to the first-floor ceiling slab, while in Building C, the ceiling slabs between the basement levels are currently being constructed.