Construction at the AVICO Greentop residential park is advancing steadily. Windows have already been installed, and facade work is now underway. On the rooftop, professionals are applying waterproofing layers.

Meanwhile, on the first three floors, bathroom waterproofing and tiling are in progress. Plastering has been completed on the third floor, while puttying continues on the lower levels. Screeding is currently taking place on the fourth floor.

On the fifth floor, basic mechanical and electrical installation is ongoing, with teams positioning cables and pipes in their final locations.

In the coming weeks, the focus will shift to tiling, painting, and further facade work.

Greentop is getting closer each day to welcoming its new residents in December with modern, eco-conscious flats.

Latest news

2025-11-19.

Technical handover of the Blueside building begins on 8th December

2025-11-10.

Finishing work is underway in the BlueSide building

2025-11-03.

Good News from Univery Residential Park!

Request a Quote

.

.