Spring Garden – foundation works progressing well

We are pleased to inform our visitors and partners that the concrete pouring of the first foundation slab section has been successfully completed. Construction is progressing according to schedule, and this marks a significant milestone in the foundation phase of the project.
Earthworks are currently focused on excavation around the pile foundations and the replacement of the upper soil layer.
GreenTop – project status

The interior landscaping works have been completed, while gardeners are currently working on the exterior green areas to ensure that residents will soon be able to enjoy well-maintained and thoughtfully designed communal outdoor spaces connected to their homes.
The lobby flooring has been completed, and the main reception area has now reached its final appearance.
Technical Handover at the BlueSide Project

Technical handovers are currently underway at the BlueSide project, along with the commissioning of the mechanical systems and the required performance measurements. Specialists are continuously monitoring the building systems to ensure that everything is completed in accordance with the highest quality and technical standards.
Construction progress continues at GreenTop Residential Park

Construction work at the GreenTop Residential Park is progressing according to schedule.
Painting, tiling, and other interior works have started on the upper floors, marking a significant step forward in the completion of the building’s interior spaces.
BlueSide – Finishing works

Minor finishing works are underway at the BlueSide residential complex, the technical handover of the apartments has begun, and the gas meter has already been installed.
Cleaning and final touches are in progress, while the sidewalk around the building has been completed. 🌳
GreenTop – Construction Status

Landscaping works are currently underway in the inner courtyard, contributing to the final design of the communal areas.
On the ground floor, the resin flooring works have been completed, and this area is now finished.
The heat pump has been successfully commissioned, ensuring the building’s modern and energy-efficient operation.
Spring Garden – Progress of Construction Works

The construction project has reached an important milestone: the piling works were completed during the past week. In parallel, the trimming back, reinforcement, and concreting of the pile heads has begun in the area facing Reitter Ferenc Street.
Technical handover of the Blueside building begins on 8th December

We are pleased to inform our future residents that the technical handover of the Blueside building will begin on 8th December 2025.
During the process, owners will be able to take possession of their apartments with the assistance of our specialists and verify their technical condition.
Finishing work is underway in the BlueSide building

Our project has reached another important milestone: the landscaping works in the inner courtyard have been completed, giving the building’s interior spaces their final appearance.
On the upper floors, flooring installation, painting, tile repair, as well as mechanical and electrical fitting works are currently in progress.
Good News from Univery Residential Park!

We are delighted to announce that the last apartment in Univery Residential Park has found its new resident! With this special milestone, the sales phase of the residential park has officially come to an end.
In recent times, numerous families, young couples, those starting over, and investors have chosen Univery Residential Park as their home, where the modern design enhances the quality of life for its residents.