Work is progressing well at the GreenTop construction site

The project has entered its final phase, and several areas are advancing steadily.
Painting and tiling are underway on the upper floors, and parquet flooring has also begun. The exterior façade has been fully painted, and the courtyard façade is expected to be completed within a week. The tower crane has been dismantled, and the basic installations are finished, allowing the electrical and mechanical fittings to start soon. In addition, drywall installation continues in the apartments and corridors.
The construction of the Spring Garden project is progressing well

On-site, the diaphragm walls and guide beams have been completed and the anchoring of the diaphragm walls has also been finished.
Earthworks are currently underway, and as the next step, we have begun drilling and concreting the pile foundations.
Whithout compromise

Discover how the closeness of nature meets urban comfort in modern residential projects!
The article “By the Creek or on the Rooftop? Both!” showcases how the harmony of green living and city life comes to life in Budapest’s latest developments.
BlueSide – Latest news about construction

We have dismantled the tower crane and are installing it (electrical and mechanical) on all levels, the cladding and painting of the facade has been completed.
We are carrying out tinsmithing work, and the aluminum pergolas will soon be installed on both the street and interior facades.
The Spring Garden project has reached another milestone!

We have completed the diaphragm wall construction, so the worksite is now ready for the next phase.
GreenTop: The electrical and mechanical rough-in work is progressing dynamically

The tower crane will be dismantled at the end of September. The facades are being surfaced, the coloring is progressing and the gluing of the facade cladding on the ground floor will soon begin.
We will be ready with the basic electrical and mechanical installation within a week or two.
All apartments in the BlueSide project are sold out

The arrival of the BlueSide Residential Park was welcomed with great joy by those interested and they quickly snapped up the apartments on the bank of the stream.
Of course, we will keep our customers informed about the progress of the project here on the website and you can also watch the construction on the webcams.
A unique graffiti wall brightens up the Spring Garden development site